|
Plateau Creek Pipeline Replacement,
Phase 2
Grand Junction, Colorado
Project Description
The Plateau Creek Pipeline Replacement Project (Phase 2) consists of approximately
68,500 feet of 48-inch and 54-inch diameter steel pipe. The alignment of the
replacement pipeline is nominally parallel to the 65 and 330 Highways and runs
from the Jerry Creek reservoirs to the Ute Water Treatment Plant located near
Palisade, CO. Two sections of pipeline were placed in tunnels constructed along
the alignment. These tunnels, 10,200 and 3,400 feet in length, were excavated by
a 10 ft diameter hard rock tunnel boring machine. The geology along the alignment
consisted of sandstones, shales and siltstones.
Scope of Services
Working on a team headed by GEI Consultants, Inc, LACHEL & Associates, Inc. (LFA)
was involved in the development of the project from the feasibility design through
construction. Initially planned as a trenched excavation, a tunneling option was developed
to optimize the project design and to minimize environmental impacts on the creek. In the
initial stages of the project, LFA provided a feasibility level cost estimate and an initial
constructibility analysis. As the project progressed, LFA provided a complete design for
the tunnel portions of the projects. This work included developing the expected ground
loads based on empirical and finite element analysis; designing the initial and final
ground support systems for the various expected ground conditions; developing plans and
specifications; and preparing the engineer's estimate related to the tunneling portion of
the project.
LFA's post-design responsibilities began with assisting the owner during the
tender phase and continued through project completion. LFA provided construction
management services for the duration of the tunnel construction. These services
included full time, on-site Resident Engineering and Tunnel Inspection services as
well as home office design support on an as-needed basis.
Client
Ute Water Conservancy District
|
|